extension of time

Construction Dispute - quickly agreed settlement

Work had been suspended due to delays in implementing the final part of the Party Wall Award for the basement, this was enough to halt all the work. The Contractor put in a reasonable claim for compensation, to cover his losses. A meeting was arranged, however the Employer brought in a ‘Contract expert’ from Devon who informed the Contractor there was no provision in the contract for compensation.

The Contractor spoke to a surveyor who recommended Lee Kyson.

Lee discussed the situation, looked at the contract documents and suggested another meeting with the Employer. Based on Lee's advice, C attended a meeting with E and subsequently agreed a compensation figure of £12½k and received a 16 week extension of time.